Friday, September 24, 2010

As of September 24, the contractor has completed the paving of the southbound lane of traffic on Old Willow Road. Beginning Monday, September 27th, traffic will be switched to the new pavement. All driveways and entrances on the west side of the road will be completed and open for traffic Monday morning.

The contractor will then proceed with the removal and replacement of the northbound lane. The traffic detour will remain one way, southbound and access to all businesses will be maintained during this time. You may experience short delays while trucks are being loaded and unloaded. Please adjust your schedules accordingly.

Friday, September 17, 2010

Pavement removal, earth excavation and aggregate base preparation will be completed on the west half of Old Willow Road this week. The Contractor is scheduled to start concrete paving (weather permitting) this Friday, September 17. Only (one-way) southbound traffic is permitted on Old Willow Road.

Friday, September 10, 2010

Pavement removal and earth excavation has started on the west half of Old Willow Road this week. Only (one-way) southbound traffic is permitted on Old Willow Road. The contractor will continue preparing the aggregate base course for paving into the next week.

Thursday, September 2, 2010

Storm sewer installation is now complete. Pavement removal will begin September 7th, in the Southbound lane. Traffic detour will remain in effect.