Friday, August 27, 2010

Installation of storm sewer is underway and should be complete next week! After all the storm sewer is in place, the contractor will start removal of existing pavement. The southbound lane of Old Willow Road will remain open to traffic and the northbound lane will remain closed.

Friday, August 20, 2010

The storm sewer work continues to progress, and should last another week or two.

Friday, August 13, 2010

The contractor has started construction this week. Due to an accelerated construction schedule, we will be closing the road to one-way traffic, southbound only, from Willow Road to Ravine Way. All driveways and entrances on Old Willow must be accessed from the north, on Willow Road. Northbound traffic will be detoured around Ravine Way. This detour will remain in place until November. See map below…

The contractor will be installation new storm sewer for the next several weeks.

NORTHBOUND DETOUR


View Larger Map