Monday, December 6, 2010

Work is substantially complete with the exception of punch list work.

Tuesday, November 30, 2010

Work is substantially complete with the exception of punch list work.

Monday, November 22, 2010

The contractor is substantially complete with work with the exception of seeding, remaining pavement markings and punch list work.

Wednesday, November 10, 2010

The contractor is substantially complete with work with the exception of seeding, pavement markings, minor storm sewer work (completing this week), and punch list work.

Friday, November 5, 2010

The contractor is substantially complete with work with the exception of seeding, pavement markings, minor storm sewer work, and punch list work.

Monday, November 1, 2010

The contractor will continue with parkway restoration with topsoil, seed and erosion control blanket this week.

Friday, October 22, 2010

The contractor is scheduled to resurface the asphalt pavement at the north and south limits late this week. The contractor will continue with parkway grading and topsoil next week.