Wednesday, November 10, 2010

The contractor is substantially complete with work with the exception of seeding, pavement markings, minor storm sewer work (completing this week), and punch list work.

Friday, November 5, 2010

The contractor is substantially complete with work with the exception of seeding, pavement markings, minor storm sewer work, and punch list work.

Monday, November 1, 2010

The contractor will continue with parkway restoration with topsoil, seed and erosion control blanket this week.

Friday, October 22, 2010

The contractor is scheduled to resurface the asphalt pavement at the north and south limits late this week. The contractor will continue with parkway grading and topsoil next week.

Friday, October 15, 2010

The contractor is scheduled to grind the existing asphalt pavement at the north and south limits next week. The contractor will continue with parkway grading next week.

Friday, October 8, 2010

The contractor is scheduled to continue installing curb and gutter and driveway aprons along the east lane of Old Willow next week. The contractor will continue with parkway grading next week.

Friday, October 1, 2010


The contractor is scheduled to pave the east lane of Old Willow this Saturday, October 2, 2010. The traffic detour will remain one way, southbound and access to all businesses will be maintained during this time. You may experience short delays while concrete trucks delivering concrete. Please adjust your schedules accordingly.

Next week, the contractor is scheduled to install the curb and gutter and driveway aprons along the east lane of Old Willow.