Friday, October 15, 2010

The contractor is scheduled to grind the existing asphalt pavement at the north and south limits next week. The contractor will continue with parkway grading next week.

Friday, October 8, 2010

The contractor is scheduled to continue installing curb and gutter and driveway aprons along the east lane of Old Willow next week. The contractor will continue with parkway grading next week.

Friday, October 1, 2010


The contractor is scheduled to pave the east lane of Old Willow this Saturday, October 2, 2010. The traffic detour will remain one way, southbound and access to all businesses will be maintained during this time. You may experience short delays while concrete trucks delivering concrete. Please adjust your schedules accordingly.

Next week, the contractor is scheduled to install the curb and gutter and driveway aprons along the east lane of Old Willow.

Friday, September 24, 2010

As of September 24, the contractor has completed the paving of the southbound lane of traffic on Old Willow Road. Beginning Monday, September 27th, traffic will be switched to the new pavement. All driveways and entrances on the west side of the road will be completed and open for traffic Monday morning.

The contractor will then proceed with the removal and replacement of the northbound lane. The traffic detour will remain one way, southbound and access to all businesses will be maintained during this time. You may experience short delays while trucks are being loaded and unloaded. Please adjust your schedules accordingly.

Friday, September 17, 2010

Pavement removal, earth excavation and aggregate base preparation will be completed on the west half of Old Willow Road this week. The Contractor is scheduled to start concrete paving (weather permitting) this Friday, September 17. Only (one-way) southbound traffic is permitted on Old Willow Road.

Friday, September 10, 2010

Pavement removal and earth excavation has started on the west half of Old Willow Road this week. Only (one-way) southbound traffic is permitted on Old Willow Road. The contractor will continue preparing the aggregate base course for paving into the next week.

Thursday, September 2, 2010

Storm sewer installation is now complete. Pavement removal will begin September 7th, in the Southbound lane. Traffic detour will remain in effect.