Friday, September 17, 2010

Pavement removal, earth excavation and aggregate base preparation will be completed on the west half of Old Willow Road this week. The Contractor is scheduled to start concrete paving (weather permitting) this Friday, September 17. Only (one-way) southbound traffic is permitted on Old Willow Road.

Friday, September 10, 2010

Pavement removal and earth excavation has started on the west half of Old Willow Road this week. Only (one-way) southbound traffic is permitted on Old Willow Road. The contractor will continue preparing the aggregate base course for paving into the next week.

Thursday, September 2, 2010

Storm sewer installation is now complete. Pavement removal will begin September 7th, in the Southbound lane. Traffic detour will remain in effect.

Friday, August 27, 2010

Installation of storm sewer is underway and should be complete next week! After all the storm sewer is in place, the contractor will start removal of existing pavement. The southbound lane of Old Willow Road will remain open to traffic and the northbound lane will remain closed.

Friday, August 20, 2010

The storm sewer work continues to progress, and should last another week or two.

Friday, August 13, 2010

The contractor has started construction this week. Due to an accelerated construction schedule, we will be closing the road to one-way traffic, southbound only, from Willow Road to Ravine Way. All driveways and entrances on Old Willow must be accessed from the north, on Willow Road. Northbound traffic will be detoured around Ravine Way. This detour will remain in place until November. See map below…

The contractor will be installation new storm sewer for the next several weeks.